24 November 2013
We have passed all of our cover inspections and insulation and sheetrock are underway.
 |
Here is Jason (electrician) enjoying his last day of rough in and passing his inspection
|
We had to have a large hole drilled through the brick for the 8" range hood exhaust pipe
 |
| Furnace up and running |
 |
| Insulation in basement |
 |
| Sheetrock delivery |
11/27
Sheetrock is almost done. Here is the latest installment the day before Thanksgiving! Use your imagination; things are going to come together very quickly from here!
 |
| new kitchen layout; sink, dishwasher, etc |
 |
| bench and stove |
 |
| sink area |
 |
| bench and stove |
 |
| bonus storage built-in(ish) |
 |
| old windows get new life |
 |
| laundry and new water heater from bottom of stairwell (at basement) |
 |
| big basement addition from laundry |
 |
| basement from laundry 2 |
 |
| basement from north door |
 |
| basement from south door |
 |
| "office" windows |
 |
| furnace room !!!! zoning feeders..... shit is cookin' |
 |
| basement shower: |
 |
| basement bathroom vanity location |
 |
| clawfoot tub locale |
 |
| clawfoot getting refinished! |
 |
| clawfoot beatified |
 |
| main floor bath floor heat wiring; basement floor bath also has floor heat in which we had to add a insulation membrane for optimal performance against the concrete slab heat loss |
EAT, DRINK, BE MERRY.... AND BUILD SOME MORE!
12/16
Finish phase is well underway. Tile, trim, cabinetry are all happening. Here are a couple recent photos. More to come this week.
 |
| hearth tile layout |
 |
| basement shower |
 |
| basement bath floor |
 |
| basement bath vanity carcass and floor |
 |
| salvaged fir case and base in basement |
 |
| master bed built in closet carcasses |
1/11/14
So it has been a while since i've made an installment. we all have opened our presents, celebrated a new year, an we are now welcoming the rain to the northwest. the job is approaching finishes, but that also means a lot of the surfaces are covered for protection! (not that good for pictures). here are some that should continue the curiosity and show some finishes already completed.
 |
| gerheart (left) and vladimir doing the miles of tile in the master bath |
 |
| wainscot turning transition to the shower |
 |
| floor and shower entry |
 |
| shower ledge and infinity drain in the shower |
 |
| countertop (covered) with incorporated sill for the window |
 |
| crema marfil countertop for master |
 |
| new hearth tile |
The upstairs also has had the floors sanded and one coat of finish.
 |
| basement just waiting for carpet, paint and a new door! |
Many more pictures to come shortly.